Mirani Waste Water Project
Project details
A valued agricultural client - Battaia Farming, asked our experienced dam-building team to design and construct a sump and dam, utilising the least amount of material for the largest economically constructed dam. We completed a survey of the existing area and carried out a 3D modelling design of the sump and water storage. Once our client approved the 150 Megalitre storage, we carried out all topsoil stripping, key trenching for the core and wall embankment and re-topsoiling before final trimming. We uploaded the GPS design file to all machines to control all design and construction requirements. We completed this project in three weeks, and the following day after completion, the client received heavy rain and started to store valuable irrigation water.